New 6-month delay UPRERAPRJ15487

The Hemisphere_royalgolf Plaza

by Royalgolf Link City Projects Private Limited · Gautam Buddha Nagar

Completion on record
08 Jun 2023
Declared 09 Dec 2022 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ15487
Gautam Buddha Nagar
Registered
22 Mar 2018
Type: New
Proposed period
57 mo
from 12 Mar 2018
Declared completion
09 Dec 2022
original commitment
Latest on record
08 Jun 2023
after 1 extension
Documents on portal
17
filed with UP-RERA
01

Registration details

Project name
The Hemisphere_royalgolf Plaza
RERA registration no.
UPRERAPRJ15487
Registration type
New
Registration date
22 Mar 2018
Proposed start
12 Mar 2018
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 09 Dec 2022 to 08 Jun 2023 over 1 registered extension.

#FromToΔReason on record
109 Dec 202208 Jun 2023+6moSix months extension in view of force...
Net slip vs first declared date+6moto 08 Jun 2023

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Royalgolf Link City Projects Private Limited
Type
Company
Registered office
M-4, GROUND & FIRST LEVEL, OFFICE NO-126 SOUTH EXTENSION PART-II NEW DELHI South West Delhi 110049
Projects on the register
5
Complaints · promoter-wide
364364 (Under Registration - 0 )
Complaints · this project
13filed against The...

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is The Hemisphere_Royalgolf Plaza RERA registered?

Yes. The Hemisphere_Royalgolf Plaza is registered with UP-RERA under registration number UPRERAPRJ15487, registered on 22 Mar 2018.

Is The Hemisphere_Royalgolf Plaza delayed?

Yes. It was declared for completion by 09 Dec 2022, but the date on record is now 08 Jun 2023, a slip of about 6 months across 1 registered extension.

Who is the developer of The Hemisphere_Royalgolf Plaza?

Royalgolf Link City Projects Private Limited, which has 5 project(s) registered with UP-RERA and 364 complaint(s) on record across its projects.

How many complaints are filed against The Hemisphere_Royalgolf Plaza?

13 complaint(s) are recorded against The Hemisphere_Royalgolf Plaza specifically on the UP-RERA portal.

Where can I verify The Hemisphere_Royalgolf Plaza's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ15487. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind The Hemisphere_royalgolf Plaza. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation