Registration details
- Project name
- The Hemisphere_royalgolf Plaza
- RERA registration no.
- UPRERAPRJ15487
- Registration type
- New
- Registration date
- 22 Mar 2018
- Proposed start
- 12 Mar 2018
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 09 Dec 2022 to 08 Jun 2023 over 1 registered extension.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 09 Dec 2022 | 08 Jun 2023 | +6mo | Six months extension in view of force... |
| Net slip vs first declared date | +6mo | to 08 Jun 2023 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Royalgolf Link City Projects Private Limited
- Type
- Company
- Registered office
- M-4, GROUND & FIRST LEVEL, OFFICE NO-126 SOUTH EXTENSION PART-II NEW DELHI South West Delhi 110049
- Projects on the register
- 5
- Complaints · promoter-wide
- 364364 (Under Registration - 0 )
- Complaints · this project
- 13filed against The...
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
17 documents filed on the UP-RERA portal for UPRERAPRJ15487. Each opens on the official portal record.
More from Royalgolf Link City...
Other projects nearby
Frequently asked
Is The Hemisphere_Royalgolf Plaza RERA registered?
Yes. The Hemisphere_Royalgolf Plaza is registered with UP-RERA under registration number UPRERAPRJ15487, registered on 22 Mar 2018.
Is The Hemisphere_Royalgolf Plaza delayed?
Yes. It was declared for completion by 09 Dec 2022, but the date on record is now 08 Jun 2023, a slip of about 6 months across 1 registered extension.
Who is the developer of The Hemisphere_Royalgolf Plaza?
Royalgolf Link City Projects Private Limited, which has 5 project(s) registered with UP-RERA and 364 complaint(s) on record across its projects.
How many complaints are filed against The Hemisphere_Royalgolf Plaza?
13 complaint(s) are recorded against The Hemisphere_Royalgolf Plaza specifically on the UP-RERA portal.
Where can I verify The Hemisphere_Royalgolf Plaza's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ15487. This page mirrors that public record for convenience.