New 18-month delay UPRERAPRJ16612

Migsun Vilaasa

by Yamuna Builtech Private Limited · Gautam Buddha Nagar

Completion on record
10 Dec 2024
Declared 12 Jun 2023 · slipped 18 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ16612
Gautam Buddha Nagar
Registered
19 Jun 2018
Type: New
Proposed period
60 mo
from 01 Jul 2018
Declared completion
12 Jun 2023
original commitment
Latest on record
10 Dec 2024
after 2 extensions
Documents on portal
15
filed with UP-RERA
01

Registration details

Project name
Migsun Vilaasa
RERA registration no.
UPRERAPRJ16612
Registration type
New
Registration date
19 Jun 2018
Proposed start
01 Jul 2018
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+18months later than promised

Declared completion moved from 12 Jun 2023 to 10 Dec 2024 over 2 registered extensions.

#FromToΔReason on record
112 Jun 202311 Dec 2023+6moSix months extension in view of force...
211 Dec 202310 Dec 2024+12mo
Net slip vs first declared date+18moto 10 Dec 2024

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Yamuna Builtech Private Limited
Type
Company
Registered office
C-2, MAHALUXMI MALL, 5TH FLOOR, RAJ NAGAR, GHAZIABAD.
Projects on the register
1
Complaints · promoter-wide
9393 (Under Registration - 1 )
Complaints · this project
89filed against Migsun Vilaasa

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

06

Frequently asked

Is Migsun Vilaasa RERA registered?

Yes. Migsun Vilaasa is registered with UP-RERA under registration number UPRERAPRJ16612, registered on 19 Jun 2018.

Is Migsun Vilaasa delayed?

Yes. It was declared for completion by 12 Jun 2023, but the date on record is now 10 Dec 2024, a slip of about 18 months across 2 registered extensions.

Who is the developer of Migsun Vilaasa?

Yamuna Builtech Private Limited, which has 1 project(s) registered with UP-RERA and 93 complaint(s) on record across its projects.

How many complaints are filed against Migsun Vilaasa?

89 complaint(s) are recorded against Migsun Vilaasa specifically on the UP-RERA portal.

Where can I verify Migsun Vilaasa's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ16612. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Migsun Vilaasa. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation