Registration details
- Project name
- Presithum Phase Ii
- RERA registration no.
- UPRERAPRJ17502
- Registration type
- New
- Registration date
- 02 Sep 2018
- Proposed start
- 01 May 2018
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 30 Dec 2023 to 28 Jun 2025 over 2 registered extensions.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 30 Dec 2023 | 29 Jun 2024 | +6mo | Six months extension in view of force... |
| 2 | 29 Jun 2024 | 28 Jun 2025 | +12mo | — |
| Net slip vs first declared date | +18mo | to 28 Jun 2025 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Presidency Infraheights Private Limited
- Type
- Company
- Registered office
- UNIT NO.2201, SECOND FLOOR, TOWER NO 2, EXPRESS TRADE TOWER-2, PLOT NO.36, SECTOR-132
- Projects on the register
- 2
- Complaints · promoter-wide
- 6868 (Under Registration - 9 )
- Complaints · this project
- 27filed against Presithum Phase Ii
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
15 documents filed on the UP-RERA portal for UPRERAPRJ17502. Each opens on the official portal record.
More from Presidency...
Other projects nearby
Frequently asked
Is Presithum Phase Ii RERA registered?
Yes. Presithum Phase Ii is registered with UP-RERA under registration number UPRERAPRJ17502, registered on 02 Sep 2018.
Is Presithum Phase Ii delayed?
Yes. It was declared for completion by 30 Dec 2023, but the date on record is now 28 Jun 2025, a slip of about 18 months across 2 registered extensions.
Who is the developer of Presithum Phase Ii?
Presidency Infraheights Private Limited, which has 2 project(s) registered with UP-RERA and 68 complaint(s) on record across its projects.
How many complaints are filed against Presithum Phase Ii?
27 complaint(s) are recorded against Presithum Phase Ii specifically on the UP-RERA portal.
Where can I verify Presithum Phase Ii's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ17502. This page mirrors that public record for convenience.
Want to go through this file before you commit?
Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Presithum Phase Ii. Straight answers, before you sign anything.
Private line · no obligation