New 35-month delay UPRERAPRJ15465

The Hemisphere_phase-1_towers

by Royalgolf Link City Projects Private Limited · Gautam Buddha Nagar

Completion on record
17 Nov 2025
Declared 09 Dec 2022 · slipped 35 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ15465
Gautam Buddha Nagar
Registered
17 Mar 2018
Type: New
Proposed period
57 mo
from 12 Mar 2018
Declared completion
09 Dec 2022
original commitment
Latest on record
17 Nov 2025
after 3 extensions
Documents on portal
17
filed with UP-RERA
01

Registration details

Project name
The Hemisphere_phase-1_towers
RERA registration no.
UPRERAPRJ15465
Registration type
New
Registration date
17 Mar 2018
Proposed start
12 Mar 2018
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+35months later than promised

Declared completion moved from 09 Dec 2022 to 17 Nov 2025 over 3 registered extensions.

#FromToΔReason on record
109 Dec 202208 Jun 2023+6moSix months extension in view of force...
208 Jun 202307 Mar 2025+21mo
307 Mar 202517 Nov 2025+8mo
Net slip vs first declared date+35moto 17 Nov 2025

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Royalgolf Link City Projects Private Limited
Type
Company
Registered office
M-4, GROUND & FIRST LEVEL, OFFICE NO-126 SOUTH EXTENSION PART-II NEW DELHI South West Delhi 110049
Projects on the register
5
Complaints · promoter-wide
364364 (Under Registration - 0 )
Complaints · this project
93filed against The Hemisphere_phase-1_towers

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is The Hemisphere_Phase-1_Towers RERA registered?

Yes. The Hemisphere_Phase-1_Towers is registered with UP-RERA under registration number UPRERAPRJ15465, registered on 17 Mar 2018.

Is The Hemisphere_Phase-1_Towers delayed?

Yes. It was declared for completion by 09 Dec 2022, but the date on record is now 17 Nov 2025, a slip of about 35 months across 3 registered extensions.

Who is the developer of The Hemisphere_Phase-1_Towers?

Royalgolf Link City Projects Private Limited, which has 5 project(s) registered with UP-RERA and 364 complaint(s) on record across its projects.

How many complaints are filed against The Hemisphere_Phase-1_Towers?

93 complaint(s) are recorded against The Hemisphere_Phase-1_Towers specifically on the UP-RERA portal.

Where can I verify The Hemisphere_Phase-1_Towers's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ15465. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind The Hemisphere_phase-1_towers. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation