Registration details
- Project name
- Aig Royal (Phase 1)
- RERA registration no.
- UPRERAPRJ17394
- Registration type
- New
- Registration date
- 20 Aug 2018
- Proposed start
- 01 Aug 2018
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 20 Jun 2023 to 19 Dec 2023 over 1 registered extension.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 20 Jun 2023 | 19 Dec 2023 | +6mo | Six months extension in view of force... |
| Net slip vs first declared date | +6mo | to 19 Dec 2023 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Alpine Infraprojects Pvt Ltd
- Type
- Company
- Registered office
- chamber no.11, vindhyachal apartment, kaushambi, Ghaziabad, U.P. 201010
- Projects on the register
- 4
- Complaints · promoter-wide
- 2424 (Under Registration - 0 )
- Complaints · this project
- 21filed against Aig Royal (Phase 1)
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
15 documents filed on the UP-RERA portal for UPRERAPRJ17394. Each opens on the official portal record.
Other projects nearby
Frequently asked
Is Aig Royal (Phase 1) RERA registered?
Yes. Aig Royal (Phase 1) is registered with UP-RERA under registration number UPRERAPRJ17394, registered on 20 Aug 2018.
Is Aig Royal (Phase 1) delayed?
Yes. It was declared for completion by 20 Jun 2023, but the date on record is now 19 Dec 2023, a slip of about 6 months across 1 registered extension.
Who is the developer of Aig Royal (Phase 1)?
Alpine Infraprojects Pvt Ltd, which has 4 project(s) registered with UP-RERA and 24 complaint(s) on record across its projects.
How many complaints are filed against Aig Royal (Phase 1)?
21 complaint(s) are recorded against Aig Royal (Phase 1) specifically on the UP-RERA portal.
Where can I verify Aig Royal (Phase 1)'s RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ17394. This page mirrors that public record for convenience.