New 21-month delay UPRERAPRJ17739

Central Plaza

by Aims Angel Infratech Llp · Gautam Buddha Nagar

Completion on record
31 Dec 2022
Declared 31 Mar 2021 · slipped 21 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ17739
Gautam Buddha Nagar
Registered
10 Oct 2018
Type: New
Proposed period
30 mo
from 01 Oct 2018
Declared completion
31 Mar 2021
original commitment
Latest on record
31 Dec 2022
after 2 extensions
Documents on portal
15
filed with UP-RERA
01

Registration details

Project name
Central Plaza
RERA registration no.
UPRERAPRJ17739
Registration type
New
Registration date
10 Oct 2018
Proposed start
01 Oct 2018
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+21months later than promised

Declared completion moved from 31 Mar 2021 to 31 Dec 2022 over 2 registered extensions.

#FromToΔReason on record
131 Mar 202130 Sep 2021+6moSix months extension in view of force...
230 Sep 202131 Dec 2022+15mo
Net slip vs first declared date+21moto 31 Dec 2022

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Aims Angel Infratech Llp
Type
Partnership Firm
Registered office
I-1, GH-04, Sector- 4, Greater Noida (West) , Uttar Pradesh, 201308
Projects on the register
1
Complaints · promoter-wide
00 (Under Registration - 0 )
Complaints · this project
0filed against Central Plaza

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

06

Frequently asked

Is Central Plaza RERA registered?

Yes. Central Plaza is registered with UP-RERA under registration number UPRERAPRJ17739, registered on 10 Oct 2018.

Is Central Plaza delayed?

Yes. It was declared for completion by 31 Mar 2021, but the date on record is now 31 Dec 2022, a slip of about 21 months across 2 registered extensions.

Who is the developer of Central Plaza?

Aims Angel Infratech Llp, which has 1 project(s) registered with UP-RERA and 0 complaint(s) on record across its projects.

How many complaints are filed against Central Plaza?

0 complaint(s) are recorded against Central Plaza specifically on the UP-RERA portal.

Where can I verify Central Plaza's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ17739. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Central Plaza. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation