Registration details
- Project name
- Wmcc-3e
- RERA registration no.
- UPRERAPRJ3337
- Registration type
- Ongoing
- Registration date
- 28 Jul 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 30 Jun 2020 to 29 Dec 2020 over 1 registered extension.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 30 Jun 2020 | 29 Dec 2020 | +6mo | Six months extension in view of force... |
| Net slip vs first declared date | +6mo | to 29 Dec 2020 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Wave Megacity Centre Pvt. Ltd.
- Type
- Company
- Registered office
- M-4, Mezzanine Floor, South Extension Part-II, New Delhi-110049
- Projects on the register
- 5
- Complaints · promoter-wide
- 880880 (Under Registration - 1 )
- Complaints · this project
- 289filed against Wmcc-3e
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
45 documents filed on the UP-RERA portal for UPRERAPRJ3337. Each opens on the official portal record.
More from Wave Megacity Centre Pvt. Ltd.
Other projects nearby
Frequently asked
Is Wmcc-3E RERA registered?
Yes. Wmcc-3E is registered with UP-RERA under registration number UPRERAPRJ3337, registered on 28 Jul 2017.
Is Wmcc-3E delayed?
Yes. It was declared for completion by 30 Jun 2020, but the date on record is now 29 Dec 2020, a slip of about 6 months across 1 registered extension.
Who is the developer of Wmcc-3E?
Wave Megacity Centre Pvt. Ltd., which has 5 project(s) registered with UP-RERA and 880 complaint(s) on record across its projects.
How many complaints are filed against Wmcc-3E?
289 complaint(s) are recorded against Wmcc-3E specifically on the UP-RERA portal.
Where can I verify Wmcc-3E's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ3337. This page mirrors that public record for convenience.
Want to go through this file before you commit?
Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Wmcc-3e. Straight answers, before you sign anything.