Ongoing 6-month delay UPRERAPRJ3011

Wmcc-2d

by Wave Megacity Centre Pvt. Ltd. · Gautam Buddha Nagar

Completion on record
30 Jun 2021
Declared 31 Dec 2020 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ3011
Gautam Buddha Nagar
Registered
28 Jul 2017
Type: Ongoing
Proposed period
96 mo
Declared completion
31 Dec 2020
original commitment
Latest on record
30 Jun 2021
after 1 extension
Documents on portal
65
filed with UP-RERA
01

Registration details

Project name
Wmcc-2d
RERA registration no.
UPRERAPRJ3011
Registration type
Ongoing
Registration date
28 Jul 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 31 Dec 2020 to 30 Jun 2021 over 1 registered extension.

#FromToΔReason on record
131 Dec 202030 Jun 2021+6moSix months extension in view of force...
Net slip vs first declared date+6moto 30 Jun 2021

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Wave Megacity Centre Pvt. Ltd.
Type
Company
Registered office
M-4, Mezzanine Floor, South Extension Part-II, New Delhi-110049
Projects on the register
5
Complaints · promoter-wide
880880 (Under Registration - 1 )
Complaints · this project
182filed against Wmcc-2d

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Wmcc-2D RERA registered?

Yes. Wmcc-2D is registered with UP-RERA under registration number UPRERAPRJ3011, registered on 28 Jul 2017.

Is Wmcc-2D delayed?

Yes. It was declared for completion by 31 Dec 2020, but the date on record is now 30 Jun 2021, a slip of about 6 months across 1 registered extension.

Who is the developer of Wmcc-2D?

Wave Megacity Centre Pvt. Ltd., which has 5 project(s) registered with UP-RERA and 880 complaint(s) on record across its projects.

How many complaints are filed against Wmcc-2D?

182 complaint(s) are recorded against Wmcc-2D specifically on the UP-RERA portal.

Where can I verify Wmcc-2D's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ3011. This page mirrors that public record for convenience.