Registration details
- Project name
- Spectrum Metro
- RERA registration no.
- UPRERAPRJ17035
- Registration type
- New
- Registration date
- 16 Jul 2018
- Proposed start
- 01 Nov 2018
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 01 Nov 2023 to 02 Nov 2024 over 2 registered extensions.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 01 Nov 2023 | 30 Apr 2024 | +5mo | Six months extension in view of force... |
| 2 | 30 Apr 2024 | 02 Nov 2024 | +7mo | — |
| Net slip vs first declared date | +12mo | to 02 Nov 2024 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Blue Square Infrastructure Llp
- Type
- Partnership Firm
- Registered office
- Unit-219 S/F Vasundhara Enclave, Plot No. 1, Vardhman Sunrise Plaza LSC, New Delhi-110096
- Projects on the register
- 6
- Complaints · promoter-wide
- 4949 (Under Registration - 4 )
- Complaints · this project
- 13filed against Spectrum Metro
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
15 documents filed on the UP-RERA portal for UPRERAPRJ17035. Each opens on the official portal record.
More from Blue Square Infrastructure Llp
Other projects nearby
Frequently asked
Is Spectrum Metro RERA registered?
Yes. Spectrum Metro is registered with UP-RERA under registration number UPRERAPRJ17035, registered on 16 Jul 2018.
Is Spectrum Metro delayed?
Yes. It was declared for completion by 01 Nov 2023, but the date on record is now 02 Nov 2024, a slip of about 12 months across 2 registered extensions.
Who is the developer of Spectrum Metro?
Blue Square Infrastructure Llp, which has 6 project(s) registered with UP-RERA and 49 complaint(s) on record across its projects.
How many complaints are filed against Spectrum Metro?
13 complaint(s) are recorded against Spectrum Metro specifically on the UP-RERA portal.
Where can I verify Spectrum Metro's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ17035. This page mirrors that public record for convenience.