New No extensions UPRERAPRJ361748/06/2025

Sobha Aurum

by Sobha Limited · Gautam Buddha Nagar

Completion on record
30 Apr 2030
Declared at registration · no extensions filed
Speak with an advisor
Sobha Aurum, project image
Development Work Plan filed with UP-RERA for this project, view on the portal ↗
Overview Land & costProgressLocationEscrowTeamDevelopment Promoter Documents FAQ
RERA number
UPRERAPRJ361748/06/2025
Gautam Buddha Nagar
Registered
17 Jun 2025
Type: New
Proposed period
58 mo
from 01 Jul 2025
Declared completion
30 Apr 2030
original commitment
Latest on record
30 Apr 2030
unchanged
Documents on portal
23
filed with UP-RERA
01

Registration details

Project name
Sobha Aurum
RERA registration no.
UPRERAPRJ361748/06/2025
Registration type
New
Registration date
17 Jun 2025
Proposed start
01 Jul 2025
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
B-255, Sector 36, Greater Noida, U.P.
Record source
up-rera.in
02

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Sobha Limited
Type
Company
Registered office
Sobha Limited, Sarjapur-Marthahalli Outer Ring Road, Bellandur Post, Bangalore - 560103
Projects on the register
2
Complaints · promoter-wide
00 (Under Registration - 0 )
Complaints · this project
0filed against Sobha Aurum

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

04

Land, build & cost

Transcribed from this project's certificates (CA, architect, engineer and development filings) on the UP-RERA portal. Figures are on the public record; verify at up-rera.in before acting.

View the source certificate (PDF) →
Land area
3.46 ac
14,001 m²
Project size
2.0 bldgs
Total carpet area
16,001
m² · project total
Project cost
₹809 Cr
construction ₹594 Cr
Cost incurred
₹176 Cr
21.8% of estimated cost
From allottees
₹0 Cr
collected to date
05

Construction progress

How far the money and the build clock have moved, from the certified figures on the project's filings. View the source certificate (PDF) →

Certified spend22%
of the estimated project cost, certified spent to date
Build clock23%
of the registered build period elapsed
Physical build0%
of construction complete, per the engineer's certificate

Certified spend is broadly keeping pace with the build timeline.

A snapshot from certified filings, not a live feed; the build clock is computed from the registered start and current completion date. Verify at up-rera.in.

06

Location

Coordinates and site details as filed on the project's certificate. View the source certificate (PDF) →

Coordinates
28.4605, 77.5410833
07

Bank account

The collection account into which buyers deposit, as named on the project's certificate filed with UP-RERA. View the source certificate (PDF) →

Collection account
A/c no. 57500001748662
08

Project team

The consultants named on the project's architect and engineer certificates. View the source certificate (PDF) →

Architect
VENKATESH GUDILicence CA/2005/36913
Structural engineer
OUSEPPACHAN C. AMBOOKENM/s. SOBHA LIMITED
09

Development & infrastructure

Committed works as stated in the project's development affidavit on the portal. View the source certificate (PDF) →

Sewage Treatment Plant
Located at Basement 2nd & 3rd
Electrical Rooms
Located at Ground Level
Transformer Yard
Located at Ground Level
DG Room
Located at Basement 2 Level
Fire Safety System
Includes Single Yard Hydrant with Hose Box, 4-Way FBC, 2-Way FBC
Underground Water Tank
Located at Basement -01, 02 & 03
Water Supply Source
Municipal/Tanker Water/Borewell water to UG Tank
Rainwater Harvesting Tank
Capacity: 200 KL, located at Ground Floor
Boundary Wall
Provided along the site perimeter
Roads
Internal driveways, including 24m wide main driveway
Parks & Green Areas
Includes Exhibition Lawn, Amphitheatre, Tennis Court, Cricket Pitch, Canopy Grove
12

Frequently asked

Is Sobha Aurum RERA registered?

Yes. Sobha Aurum is registered with UP-RERA under registration number UPRERAPRJ361748/06/2025, registered on 17 Jun 2025.

What is the RERA completion date for Sobha Aurum?

The completion date on record is 30 Apr 2030, with no extensions filed against the original commitment.

Who is the developer of Sobha Aurum?

Sobha Limited, which has 2 project(s) registered with UP-RERA and 0 complaint(s) on record across its projects.

How many complaints are filed against Sobha Aurum?

0 complaint(s) are recorded against Sobha Aurum specifically on the UP-RERA portal.

Where can I verify Sobha Aurum's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ361748/06/2025. This page mirrors that public record for convenience.