New No extensions UPRERAPRJ787189/12/2025

Delta Square

by Baba Projects Private Limited · Gautam Buddha Nagar

Completion on record
15 Oct 2030
Declared at registration · no extensions filed
Speak with an advisor
Delta Square, project image
Development Work Plan filed with UP-RERA for this project, view on the portal ↗
Overview Land & costProgressLocationEscrowTeamDevelopment Promoter Documents FAQ
RERA number
UPRERAPRJ787189/12/2025
Gautam Buddha Nagar
Registered
22 Dec 2025
Type: New
Proposed period
60 mo
from 01 Nov 2025
Declared completion
15 Oct 2030
original commitment
Latest on record
15 Oct 2030
unchanged
Documents on portal
18
filed with UP-RERA
01

Registration details

Project name
Delta Square
RERA registration no.
UPRERAPRJ787189/12/2025
Registration type
New
Registration date
22 Dec 2025
Proposed start
01 Nov 2025
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Plot No. SLC-08/G/6, Sector-Delta -2, Greater Noida, Gautam Buddha Nagar, Uttar Pradesh, PIN-201308
Record source
up-rera.in
02

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Baba Projects Private Limited
Type
Company
Registered office
Regd Office - House No. -2K/74, Bariatuhousing Colony, P.O.-Bariatu, P.S.-Bariatu,Ranchi, Jharkhand,PIN-834009 Corporate Offce - C-63, Block-C, Sector 58, NOIDA,Gautam Buddha Nagar,Uttar Pradesh,PIN-201301
Projects on the register
1
Complaints · promoter-wide
00 (Under Registration - 0 )
Complaints · this project
0filed against Delta Square

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

04

Land, build & cost

Transcribed from this project's certificates (CA, architect, engineer and development filings) on the UP-RERA portal. Figures are on the public record; verify at up-rera.in before acting.

View the source certificate (PDF) →
Land area
0.57 ac
2,313 m²
Project size
1.0 bldgs
Floors
18.0
Total carpet area
2,313
m² · project total
Project cost
₹137 Cr
construction ₹73 Cr
Cost incurred
₹22 Cr
16.1% of estimated cost
From allottees
₹0 Cr
collected to date
05

Construction progress

How far the money and the build clock have moved, from the certified figures on the project's filings. View the source certificate (PDF) →

Certified spend16%
of the estimated project cost, certified spent to date
Build clock15%
of the registered build period elapsed
Physical build0%
of construction complete, per the engineer's certificate

Certified spend is broadly keeping pace with the build timeline.

A snapshot from certified filings, not a live feed; the build clock is computed from the registered start and current completion date. Verify at up-rera.in.

06

Location

Coordinates and site details as filed on the project's certificate. View the source certificate (PDF) →

Coordinates
28.48626, 77.5185889
07

Bank account

The collection account into which buyers deposit, as named on the project's certificate filed with UP-RERA. View the source certificate (PDF) →

Collection account
A/c no. 30200112741648
08

Project team

The consultants named on the project's architect and engineer certificates. View the source certificate (PDF) →

Architect
RAVI RAJ JAINLicence CA/2024/170151
Structural engineer
Atul SaxenaNone
09

Development & infrastructure

Committed works as stated in the project's development affidavit on the portal. View the source certificate (PDF) →

Electric supply / transformers
Meter Room (3x3m = 9 sq.mt)
Fire safety & staircases
Fire Tower Mumty; Refuge Area provided: 45.19 sq.mt (8th floor), 47.84 sq.mt (12A floor)
Water supply / tanks
Overhead Tank (LVL +58800, 3.2x6m); Water Tank above Mumty Roof (LVL +62100); Total O.H. Tank area 45.089 sq.mt
Rainwater harvesting
Recharge pit (bore 250mm dia, 150mm slotted pipe)
Boundary wall
Constructed with stone plaster, brickwork, PCC, boulder soling; Height approx 1.95m
Roads
4.5 MT Wide Road (side), 60 MT Wide Road (front), 9 MT W Service Road
Parks
Green Area proposed 348.27 sq.mt (25.04%); 14 trees provided (7 evergreen, 7 seasonal)
11

Frequently asked

Is Delta Square RERA registered?

Yes. Delta Square is registered with UP-RERA under registration number UPRERAPRJ787189/12/2025, registered on 22 Dec 2025.

What is the RERA completion date for Delta Square?

The completion date on record is 15 Oct 2030, with no extensions filed against the original commitment.

Who is the developer of Delta Square?

Baba Projects Private Limited, which has 1 project(s) registered with UP-RERA and 0 complaint(s) on record across its projects.

How many complaints are filed against Delta Square?

0 complaint(s) are recorded against Delta Square specifically on the UP-RERA portal.

Where can I verify Delta Square's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ787189/12/2025. This page mirrors that public record for convenience.