Ongoing 18-month delay UPRERAPRJ4975

Nirala Greenshire Ph-1 (G6-G12,g14)

by Nirala Projects Private Limited · Gautam Buddha Nagar

Completion on record
29 Mar 2022
Declared 30 Sep 2020 · slipped 18 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ4975
Gautam Buddha Nagar
Registered
31 Jul 2017
Type: Ongoing
Proposed period
79 mo
Declared completion
30 Sep 2020
original commitment
Latest on record
29 Mar 2022
after 3 extensions
Documents on portal
22
filed with UP-RERA
01

Registration details

Project name
Nirala Greenshire Ph-1 (G6-G12,g14)
RERA registration no.
UPRERAPRJ4975
Registration type
Ongoing
Registration date
31 Jul 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+18months later than promised

Declared completion moved from 30 Sep 2020 to 29 Mar 2022 over 3 registered extensions.

#FromToΔReason on record
130 Sep 202029 Mar 2021+6moSix months extension in view of force...
229 Mar 202130 Sep 2021+6mo
330 Sep 202129 Mar 2022+6mo
Net slip vs first declared date+18moto 29 Mar 2022

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Nirala Projects Private Limited
Type
Company
Registered office
1113, 11TH FLOOR, KAILASH BUILDING, PLOT NO.26, KASTURBA GANDHI MARG, NEW DELHI – 110001
Projects on the register
3
Complaints · promoter-wide
1919 (Under Registration - 0 )
Complaints · this project
13filed against Nirala Greenshire...

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Nirala Greenshire Ph-1 (G6-G12,G14) RERA registered?

Yes. Nirala Greenshire Ph-1 (G6-G12,G14) is registered with UP-RERA under registration number UPRERAPRJ4975, registered on 31 Jul 2017.

Is Nirala Greenshire Ph-1 (G6-G12,G14) delayed?

Yes. It was declared for completion by 30 Sep 2020, but the date on record is now 29 Mar 2022, a slip of about 18 months across 3 registered extensions.

Who is the developer of Nirala Greenshire Ph-1 (G6-G12,G14)?

Nirala Projects Private Limited, which has 3 project(s) registered with UP-RERA and 19 complaint(s) on record across its projects.

How many complaints are filed against Nirala Greenshire Ph-1 (G6-G12,G14)?

13 complaint(s) are recorded against Nirala Greenshire Ph-1 (G6-G12,G14) specifically on the UP-RERA portal.

Where can I verify Nirala Greenshire Ph-1 (G6-G12,G14)'s RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ4975. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Nirala Greenshire Ph-1 (G6-G12,g14). Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation