Registration details
- Project name
- Greenshire Mart
- RERA registration no.
- UPRERAPRJ716227
- Registration type
- New
- Registration date
- 28 Apr 2020
- Proposed start
- 01 Mar 2020
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 31 Mar 2023 to 30 Sep 2023 over 1 registered extension.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 31 Mar 2023 | 30 Sep 2023 | +6mo | Six months extension in view of force... |
| Net slip vs first declared date | +6mo | to 30 Sep 2023 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Nirala Projects Private Limited
- Type
- Company
- Registered office
- 1113, 11TH FLOOR, KAILASH BUILDING, PLOT NO.26, KASTURBA GANDHI MARG, NEW DELHI – 110001
- Projects on the register
- 3
- Complaints · promoter-wide
- 1919 (Under Registration - 0 )
- Complaints · this project
- 0filed against Greenshire Mart
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
24 documents filed on the UP-RERA portal for UPRERAPRJ716227. Each opens on the official portal record.
More from Nirala Projects Private Limited
Other projects nearby
Frequently asked
Is Greenshire Mart RERA registered?
Yes. Greenshire Mart is registered with UP-RERA under registration number UPRERAPRJ716227, registered on 28 Apr 2020.
Is Greenshire Mart delayed?
Yes. It was declared for completion by 31 Mar 2023, but the date on record is now 30 Sep 2023, a slip of about 6 months across 1 registered extension.
Who is the developer of Greenshire Mart?
Nirala Projects Private Limited, which has 3 project(s) registered with UP-RERA and 19 complaint(s) on record across its projects.
How many complaints are filed against Greenshire Mart?
0 complaint(s) are recorded against Greenshire Mart specifically on the UP-RERA portal.
Where can I verify Greenshire Mart's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ716227. This page mirrors that public record for convenience.
Want to go through this file before you commit?
Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Greenshire Mart. Straight answers, before you sign anything.
Private line · no obligation