Registration details
- Project name
- Gulshan Dynasty
- RERA registration no.
- UPRERAPRJ950870
- Registration type
- New
- Registration date
- 19 Nov 2019
- Proposed start
- 25 Nov 2019
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 30 Nov 2024 to 29 Mar 2025 over 1 registered extension.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 30 Nov 2024 | 29 Mar 2025 | +4mo | — |
| Net slip vs first declared date | +4mo | to 29 Mar 2025 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Gulshan Homz Private Limited
- Type
- Company
- Registered office
- 121,Hargovind Enclave, Delhi 110092
- Projects on the register
- 3
- Complaints · promoter-wide
- 3939 (Under Registration - 0 )
- Complaints · this project
- 0filed against Gulshan Dynasty
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
25 documents filed on the UP-RERA portal for UPRERAPRJ950870. Each opens on the official portal record.
More from Gulshan Homz Private Limited
Other projects nearby
Frequently asked
Is Gulshan Dynasty RERA registered?
Yes. Gulshan Dynasty is registered with UP-RERA under registration number UPRERAPRJ950870, registered on 19 Nov 2019.
Is Gulshan Dynasty delayed?
Yes. It was declared for completion by 30 Nov 2024, but the date on record is now 29 Mar 2025, a slip of about 4 months across 1 registered extension.
Who is the developer of Gulshan Dynasty?
Gulshan Homz Private Limited, which has 3 project(s) registered with UP-RERA and 39 complaint(s) on record across its projects.
How many complaints are filed against Gulshan Dynasty?
0 complaint(s) are recorded against Gulshan Dynasty specifically on the UP-RERA portal.
Where can I verify Gulshan Dynasty's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ950870. This page mirrors that public record for convenience.