New 6-month delay UPRERAPRJ394364

Nirala - Biz Park

by Nirala Infratech Private Limited · Gautam Buddha Nagar

Completion on record
17 May 2025
Declared 18 Nov 2024 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ394364
Gautam Buddha Nagar
Registered
28 Jan 2019
Type: New
Proposed period
72 mo
from 19 Nov 2018
Declared completion
18 Nov 2024
original commitment
Latest on record
17 May 2025
after 1 extension
Documents on portal
19
filed with UP-RERA
01

Registration details

Project name
Nirala - Biz Park
RERA registration no.
UPRERAPRJ394364
Registration type
New
Registration date
28 Jan 2019
Proposed start
19 Nov 2018
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 18 Nov 2024 to 17 May 2025 over 1 registered extension.

#FromToΔReason on record
118 Nov 202417 May 2025+6moSix months extension in view of force...
Net slip vs first declared date+6moto 17 May 2025

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Nirala Infratech Private Limited
Type
Company
Registered office
H-61, 1ST FLOOR, SECTOR-63, NOIDA-201301, UTTAR PRADESH, INDIA
Projects on the register
5
Complaints · promoter-wide
88 (Under Registration - 0 )
Complaints · this project
0filed against Nirala - Biz Park

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Nirala - Biz Park RERA registered?

Yes. Nirala - Biz Park is registered with UP-RERA under registration number UPRERAPRJ394364, registered on 28 Jan 2019.

Is Nirala - Biz Park delayed?

Yes. It was declared for completion by 18 Nov 2024, but the date on record is now 17 May 2025, a slip of about 6 months across 1 registered extension.

Who is the developer of Nirala - Biz Park?

Nirala Infratech Private Limited, which has 5 project(s) registered with UP-RERA and 8 complaint(s) on record across its projects.

How many complaints are filed against Nirala - Biz Park?

0 complaint(s) are recorded against Nirala - Biz Park specifically on the UP-RERA portal.

Where can I verify Nirala - Biz Park's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ394364. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Nirala - Biz Park. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation