New 6-month delay UPRERAPRJ745601

Godrej Palm Retreat 1

by Ace Infracity Developers Private Limited · Gautam Buddha Nagar

Completion on record
03 Jun 2025
Declared 04 Dec 2024 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ745601
Gautam Buddha Nagar
Registered
11 Jun 2019
Type: New
Proposed period
64 mo
from 01 Sep 2019
Declared completion
04 Dec 2024
original commitment
Latest on record
03 Jun 2025
after 1 extension
Documents on portal
27
filed with UP-RERA
01

Registration details

Project name
Godrej Palm Retreat 1
RERA registration no.
UPRERAPRJ745601
Registration type
New
Registration date
11 Jun 2019
Proposed start
01 Sep 2019
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 04 Dec 2024 to 03 Jun 2025 over 1 registered extension.

#FromToΔReason on record
104 Dec 202403 Jun 2025+6moSix months extension in view of force...
Net slip vs first declared date+6moto 03 Jun 2025

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Ace Infracity Developers Private Limited
Type
Company
Registered office
01-B, Sector-126, Noida, U.P.
Projects on the register
4
Complaints · promoter-wide
1414 (Under Registration - 2 )
Complaints · this project
5filed against Godrej Palm Retreat 1

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Godrej Palm Retreat 1 RERA registered?

Yes. Godrej Palm Retreat 1 is registered with UP-RERA under registration number UPRERAPRJ745601, registered on 11 Jun 2019.

Is Godrej Palm Retreat 1 delayed?

Yes. It was declared for completion by 04 Dec 2024, but the date on record is now 03 Jun 2025, a slip of about 6 months across 1 registered extension.

Who is the developer of Godrej Palm Retreat 1?

Ace Infracity Developers Private Limited, which has 4 project(s) registered with UP-RERA and 14 complaint(s) on record across its projects.

How many complaints are filed against Godrej Palm Retreat 1?

5 complaint(s) are recorded against Godrej Palm Retreat 1 specifically on the UP-RERA portal.

Where can I verify Godrej Palm Retreat 1's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ745601. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Godrej Palm Retreat 1. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation