New 6-month delay UPRERAPRJ936659

The Jewel Of Noida (Phase Iv) - Avenues At Burj Noida

by E Homes Infrastructure Pvt Ltd · Gautam Buddha Nagar

Completion on record
03 May 2029
Declared 04 Nov 2028 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ936659
Gautam Buddha Nagar
Registered
02 Feb 2019
Type: New
Proposed period
120 mo
from 05 Nov 2018
Declared completion
04 Nov 2028
original commitment
Latest on record
03 May 2029
after 1 extension
Documents on portal
24
filed with UP-RERA
01

Registration details

Project name
The Jewel Of Noida (Phase Iv) - Avenues At Burj Noida
RERA registration no.
UPRERAPRJ936659
Registration type
New
Registration date
02 Feb 2019
Proposed start
05 Nov 2018
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 04 Nov 2028 to 03 May 2029 over 1 registered extension.

#FromToΔReason on record
104 Nov 202803 May 2029+6moSix months extension in view of force...
Net slip vs first declared date+6moto 03 May 2029

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
E Homes Infrastructure Pvt Ltd
Type
Company
Registered office
DASNAC ANNEXE I ECE HOUSE 28A KASTURBA GANDHI MARG NEW DELHI 110001
Projects on the register
5
Complaints · promoter-wide
1111 (Under Registration - 0 )
Complaints · this project
0filed against The Jewel Of Noida...

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is The Jewel Of Noida (Phase Iv) - Avenues At Burj Noida RERA registered?

Yes. The Jewel Of Noida (Phase Iv) - Avenues At Burj Noida is registered with UP-RERA under registration number UPRERAPRJ936659, registered on 02 Feb 2019.

Is The Jewel Of Noida (Phase Iv) - Avenues At Burj Noida delayed?

Yes. It was declared for completion by 04 Nov 2028, but the date on record is now 03 May 2029, a slip of about 6 months across 1 registered extension.

Who is the developer of The Jewel Of Noida (Phase Iv) - Avenues At Burj Noida?

E Homes Infrastructure Pvt Ltd, which has 5 project(s) registered with UP-RERA and 11 complaint(s) on record across its projects.

How many complaints are filed against The Jewel Of Noida (Phase Iv) - Avenues At Burj Noida?

0 complaint(s) are recorded against The Jewel Of Noida (Phase Iv) - Avenues At Burj Noida specifically on the UP-RERA portal.

Where can I verify The Jewel Of Noida (Phase Iv) - Avenues At Burj Noida's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ936659. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind The Jewel Of Noida (Phase Iv) - Avenues At Burj Noida. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation