Registration details
- Project name
- Winsten Park, Phase-Ii
- RERA registration no.
- UPRERAPRJ9566
- Registration type
- Ongoing
- Registration date
- 15 Aug 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 07 Jul 2021 to 23 Nov 2024 over 4 registered extensions.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 07 Jul 2021 | 06 Jan 2022 | +6mo | Six months extension in view of force... |
| 2 | 06 Jan 2022 | 05 Sep 2023 | +20mo | — |
| 3 | 05 Sep 2023 | 23 May 2024 | +8mo | — |
| 4 | 23 May 2024 | 23 Nov 2024 | +6mo | — |
| Net slip vs first declared date | +40mo | to 23 Nov 2024 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Skv Infotech Private Limited
- Type
- Company
- Registered office
- Plot No-17, Knowledge Park-V, Greater Noida (West) 201306, U.P.
- Projects on the register
- 3
- Complaints · promoter-wide
- 88 (Under Registration - 0 )
- Complaints · this project
- 3filed against Winsten Park, Phase-Ii
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
20 documents filed on the UP-RERA portal for UPRERAPRJ9566. Each opens on the official portal record.
More from Skv Infotech Private Limited
Other projects nearby
Frequently asked
Is Winsten Park, Phase-Ii RERA registered?
Yes. Winsten Park, Phase-Ii is registered with UP-RERA under registration number UPRERAPRJ9566, registered on 15 Aug 2017.
Is Winsten Park, Phase-Ii delayed?
Yes. It was declared for completion by 07 Jul 2021, but the date on record is now 23 Nov 2024, a slip of about 40 months across 4 registered extensions.
Who is the developer of Winsten Park, Phase-Ii?
Skv Infotech Private Limited, which has 3 project(s) registered with UP-RERA and 8 complaint(s) on record across its projects.
How many complaints are filed against Winsten Park, Phase-Ii?
3 complaint(s) are recorded against Winsten Park, Phase-Ii specifically on the UP-RERA portal.
Where can I verify Winsten Park, Phase-Ii's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ9566. This page mirrors that public record for convenience.
Want to go through this file before you commit?
Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Winsten Park, Phase-Ii. Straight answers, before you sign anything.
Private line · no obligation