Registration details
- Project name
- Victoryone Amara
- RERA registration no.
- UPRERAPRJ6187
- Registration type
- Ongoing
- Registration date
- 02 Aug 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarDadri
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 31 Dec 2022 to 23 Aug 2028 over 3 registered extensions.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 31 Dec 2022 | 30 Jun 2023 | +6mo | Six months extension in view of force... |
| 2 | 30 Jun 2023 | 29 Mar 2025 | +21mo | — |
| 3 | 29 Mar 2025 | 23 Aug 2028 | +41mo | — |
| Net slip vs first declared date | +68mo | to 23 Aug 2028 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Rudra Buildwell Infra Pvt. Ltd.
- Type
- Company
- Registered office
- 10-A, G/F, 40 MIG Flat, Nirman Vihar, Delhi 110092
- Projects on the register
- 1
- Complaints · promoter-wide
- 7979 (Under Registration - 0 )
- Complaints · this project
- 60filed against Victoryone Amara
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
10 documents filed on the UP-RERA portal for UPRERAPRJ6187. Each opens on the official portal record.
Other projects nearby
Frequently asked
Is Victoryone Amara RERA registered?
Yes. Victoryone Amara is registered with UP-RERA under registration number UPRERAPRJ6187, registered on 02 Aug 2017.
Is Victoryone Amara delayed?
Yes. It was declared for completion by 31 Dec 2022, but the date on record is now 23 Aug 2028, a slip of about 68 months across 3 registered extensions.
Who is the developer of Victoryone Amara?
Rudra Buildwell Infra Pvt. Ltd., which has 1 project(s) registered with UP-RERA and 79 complaint(s) on record across its projects.
How many complaints are filed against Victoryone Amara?
60 complaint(s) are recorded against Victoryone Amara specifically on the UP-RERA portal.
Where can I verify Victoryone Amara's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ6187. This page mirrors that public record for convenience.