Ongoing 12-month delay UPRERAPRJ2537

Unibera Towers

by Unibera Developers Pvt Ltd · Dadri

Completion on record
30 Nov 2019
Declared 30 Nov 2018 · slipped 12 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ2537
Gautam Buddha Nagar
Registered
31 Jul 2017
Type: Ongoing
Proposed period
58 mo
Declared completion
30 Nov 2018
original commitment
Latest on record
30 Nov 2019
after 2 extensions
Documents on portal
15
filed with UP-RERA
01

Registration details

Project name
Unibera Towers
RERA registration no.
UPRERAPRJ2537
Registration type
Ongoing
Registration date
31 Jul 2017
Proposed start
District / tehsil
Gautam Buddha NagarDadri
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+12months later than promised

Declared completion moved from 30 Nov 2018 to 30 Nov 2019 over 2 registered extensions.

#FromToΔReason on record
130 Nov 201831 May 2019+6mo
231 May 201930 Nov 2019+6mo
Net slip vs first declared date+12moto 30 Nov 2019

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Unibera Developers Pvt Ltd
Type
Company
Registered office
A-11 A, SEC-58, NOIDA
Projects on the register
2
Complaints · promoter-wide
195195 (Under Registration - 0 )
Complaints · this project
179filed against Unibera Towers

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Unibera Towers RERA registered?

Yes. Unibera Towers is registered with UP-RERA under registration number UPRERAPRJ2537, registered on 31 Jul 2017.

Is Unibera Towers delayed?

Yes. It was declared for completion by 30 Nov 2018, but the date on record is now 30 Nov 2019, a slip of about 12 months across 2 registered extensions.

Who is the developer of Unibera Towers?

Unibera Developers Pvt Ltd, which has 2 project(s) registered with UP-RERA and 195 complaint(s) on record across its projects.

How many complaints are filed against Unibera Towers?

179 complaint(s) are recorded against Unibera Towers specifically on the UP-RERA portal.

Where can I verify Unibera Towers's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ2537. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Unibera Towers. Straight answers, before you sign anything.