Ongoing 27-month delay UPRERAPRJ3627

Uchdpl-Sector-15-Plots

by Uppal Chadha Hi-Tech Developers Pvt. Ltd. · Gautam Buddha Nagar

Completion on record
27 Feb 2023
Declared 30 Nov 2020 · slipped 27 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ3627
Gautam Buddha Nagar
Registered
28 Jul 2017
Type: Ongoing
Proposed period
131 mo
Declared completion
30 Nov 2020
original commitment
Latest on record
27 Feb 2023
after 3 extensions
Documents on portal
17
filed with UP-RERA
01

Registration details

Project name
Uchdpl-Sector-15-Plots
RERA registration no.
UPRERAPRJ3627
Registration type
Ongoing
Registration date
28 Jul 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+27months later than promised

Declared completion moved from 30 Nov 2020 to 27 Feb 2023 over 3 registered extensions.

#FromToΔReason on record
130 Nov 202029 May 2021+6moSix months extension in view of force...
229 May 202128 May 2022+12mo
328 May 202227 Feb 2023+9mo
Net slip vs first declared date+27moto 27 Feb 2023

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Uppal Chadha Hi-Tech Developers Pvt. Ltd.
Type
Company
Registered office
M-4 Mezzanine Floor, South Extension Part II, New Delhi, Delhi 110049
Projects on the register
29
Complaints · promoter-wide
10551055 (Under Registration - 2 )
Complaints · this project
96filed against Uchdpl-Sector-15-Plots

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Uchdpl-Sector-15-Plots RERA registered?

Yes. Uchdpl-Sector-15-Plots is registered with UP-RERA under registration number UPRERAPRJ3627, registered on 28 Jul 2017.

Is Uchdpl-Sector-15-Plots delayed?

Yes. It was declared for completion by 30 Nov 2020, but the date on record is now 27 Feb 2023, a slip of about 27 months across 3 registered extensions.

Who is the developer of Uchdpl-Sector-15-Plots?

Uppal Chadha Hi-Tech Developers Pvt. Ltd., which has 29 project(s) registered with UP-RERA and 1055 complaint(s) on record across its projects.

How many complaints are filed against Uchdpl-Sector-15-Plots?

96 complaint(s) are recorded against Uchdpl-Sector-15-Plots specifically on the UP-RERA portal.

Where can I verify Uchdpl-Sector-15-Plots's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ3627. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Uchdpl-Sector-15-Plots. Straight answers, before you sign anything.