Ongoing 6-month delay UPRERAPRJ5539

Supertech Northeye (Phase-Ii)

by Supertech Limited · Gautam Buddha Nagar

Completion on record
29 Jun 2021
Declared 30 Dec 2020 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ5539
Gautam Buddha Nagar
Registered
10 Aug 2017
Type: Ongoing
Proposed period
113 mo
Declared completion
30 Dec 2020
original commitment
Latest on record
29 Jun 2021
after 1 extension
Documents on portal
27
filed with UP-RERA
01

Registration details

Project name
Supertech Northeye (Phase-Ii)
RERA registration no.
UPRERAPRJ5539
Registration type
Ongoing
Registration date
10 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 30 Dec 2020 to 29 Jun 2021 over 1 registered extension.

#FromToΔReason on record
130 Dec 202029 Jun 2021+6moSix months extension in view of force...
Net slip vs first declared date+6moto 29 Jun 2021

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Supertech Limited
Type
Company
Registered office
1114 HAMKUNT CHAMBERS ,11 FLOOR 89, NEHRU PLACE NEW DELHI DL 110019 INDIA
Projects on the register
27
Complaints · promoter-wide
28012801 (Under Registration - 2 )
Complaints · this project
352filed against Supertech Northeye (Phase-Ii)

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Supertech Northeye (Phase-Ii) RERA registered?

Yes. Supertech Northeye (Phase-Ii) is registered with UP-RERA under registration number UPRERAPRJ5539, registered on 10 Aug 2017.

Is Supertech Northeye (Phase-Ii) delayed?

Yes. It was declared for completion by 30 Dec 2020, but the date on record is now 29 Jun 2021, a slip of about 6 months across 1 registered extension.

Who is the developer of Supertech Northeye (Phase-Ii)?

Supertech Limited, which has 27 project(s) registered with UP-RERA and 2801 complaint(s) on record across its projects.

How many complaints are filed against Supertech Northeye (Phase-Ii)?

352 complaint(s) are recorded against Supertech Northeye (Phase-Ii) specifically on the UP-RERA portal.

Where can I verify Supertech Northeye (Phase-Ii)'s RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ5539. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Supertech Northeye (Phase-Ii). Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation