Ongoing 6-month delay UPRERAPRJ9744

Supertech Ecociti - Phase-1

by Supertech Limited · Gautam Buddha Nagar

Completion on record
30 Jun 2018
Declared 30 Dec 2017 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ9744
Gautam Buddha Nagar
Registered
12 Aug 2017
Type: Ongoing
Proposed period
93 mo
Declared completion
30 Dec 2017
original commitment
Latest on record
30 Jun 2018
after 1 extension
Documents on portal
15
filed with UP-RERA
01

Registration details

Project name
Supertech Ecociti - Phase-1
RERA registration no.
UPRERAPRJ9744
Registration type
Ongoing
Registration date
12 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 30 Dec 2017 to 30 Jun 2018 over 1 registered extension.

#FromToΔReason on record
130 Dec 201730 Jun 2018+6mo
Net slip vs first declared date+6moto 30 Jun 2018

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Supertech Limited
Type
Company
Registered office
1114 HAMKUNT CHAMBERS ,11 FLOOR 89, NEHRU PLACE NEW DELHI DL 110019 INDIA
Projects on the register
27
Complaints · promoter-wide
28012801 (Under Registration - 2 )
Complaints · this project
9filed against Supertech Ecociti - Phase-1

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Supertech Ecociti - Phase-1 RERA registered?

Yes. Supertech Ecociti - Phase-1 is registered with UP-RERA under registration number UPRERAPRJ9744, registered on 12 Aug 2017.

Is Supertech Ecociti - Phase-1 delayed?

Yes. It was declared for completion by 30 Dec 2017, but the date on record is now 30 Jun 2018, a slip of about 6 months across 1 registered extension.

Who is the developer of Supertech Ecociti - Phase-1?

Supertech Limited, which has 27 project(s) registered with UP-RERA and 2801 complaint(s) on record across its projects.

How many complaints are filed against Supertech Ecociti - Phase-1?

9 complaint(s) are recorded against Supertech Ecociti - Phase-1 specifically on the UP-RERA portal.

Where can I verify Supertech Ecociti - Phase-1's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ9744. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Supertech Ecociti - Phase-1. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation