Registration details
- Project name
- Supertech Ecociti - Phase-1
- RERA registration no.
- UPRERAPRJ9744
- Registration type
- Ongoing
- Registration date
- 12 Aug 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 30 Dec 2017 to 30 Jun 2018 over 1 registered extension.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 30 Dec 2017 | 30 Jun 2018 | +6mo | — |
| Net slip vs first declared date | +6mo | to 30 Jun 2018 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Supertech Limited
- Type
- Company
- Registered office
- 1114 HAMKUNT CHAMBERS ,11 FLOOR 89, NEHRU PLACE NEW DELHI DL 110019 INDIA
- Projects on the register
- 27
- Complaints · promoter-wide
- 28012801 (Under Registration - 2 )
- Complaints · this project
- 9filed against Supertech Ecociti - Phase-1
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
15 documents filed on the UP-RERA portal for UPRERAPRJ9744. Each opens on the official portal record.
More from Supertech Limited
Other projects nearby
Frequently asked
Is Supertech Ecociti - Phase-1 RERA registered?
Yes. Supertech Ecociti - Phase-1 is registered with UP-RERA under registration number UPRERAPRJ9744, registered on 12 Aug 2017.
Is Supertech Ecociti - Phase-1 delayed?
Yes. It was declared for completion by 30 Dec 2017, but the date on record is now 30 Jun 2018, a slip of about 6 months across 1 registered extension.
Who is the developer of Supertech Ecociti - Phase-1?
Supertech Limited, which has 27 project(s) registered with UP-RERA and 2801 complaint(s) on record across its projects.
How many complaints are filed against Supertech Ecociti - Phase-1?
9 complaint(s) are recorded against Supertech Ecociti - Phase-1 specifically on the UP-RERA portal.
Where can I verify Supertech Ecociti - Phase-1's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ9744. This page mirrors that public record for convenience.