Registration details
- Project name
- Sikka Kimantra Greens
- RERA registration no.
- UPRERAPRJ5697
- Registration type
- Ongoing
- Registration date
- 03 Aug 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 01 Feb 2022 to 30 Apr 2024 over 2 registered extensions.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 01 Feb 2022 | 31 Jul 2022 | +5mo | Six months extension in view of force... |
| 2 | 31 Jul 2022 | 30 Apr 2024 | +21mo | — |
| Net slip vs first declared date | +26mo | to 30 Apr 2024 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Pinnacle Superstructures Private Limited
- Type
- Company
- Registered office
- C-60 Preet Vihar
- Projects on the register
- 1
- Complaints · promoter-wide
- 3939 (Under Registration - 0 )
- Complaints · this project
- 35filed against Sikka Kimantra Greens
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
15 documents filed on the UP-RERA portal for UPRERAPRJ5697. Each opens on the official portal record.
Other projects nearby
Frequently asked
Is Sikka Kimantra Greens RERA registered?
Yes. Sikka Kimantra Greens is registered with UP-RERA under registration number UPRERAPRJ5697, registered on 03 Aug 2017.
Is Sikka Kimantra Greens delayed?
Yes. It was declared for completion by 01 Feb 2022, but the date on record is now 30 Apr 2024, a slip of about 26 months across 2 registered extensions.
Who is the developer of Sikka Kimantra Greens?
Pinnacle Superstructures Private Limited, which has 1 project(s) registered with UP-RERA and 39 complaint(s) on record across its projects.
How many complaints are filed against Sikka Kimantra Greens?
35 complaint(s) are recorded against Sikka Kimantra Greens specifically on the UP-RERA portal.
Where can I verify Sikka Kimantra Greens's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ5697. This page mirrors that public record for convenience.