Ongoing 27-month delay UPRERAPRJ5596

Sikka Kaamna Greens

by Kindle Infraheights Private Limited · Gautam Buddha Nagar

Completion on record
28 Sep 2022
Declared 30 Jun 2020 · slipped 27 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ5596
Gautam Buddha Nagar
Registered
03 Aug 2017
Type: Ongoing
Proposed period
99 mo
Declared completion
30 Jun 2020
original commitment
Latest on record
28 Sep 2022
after 3 extensions
Documents on portal
15
filed with UP-RERA
01

Registration details

Project name
Sikka Kaamna Greens
RERA registration no.
UPRERAPRJ5596
Registration type
Ongoing
Registration date
03 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+27months later than promised

Declared completion moved from 30 Jun 2020 to 28 Sep 2022 over 3 registered extensions.

#FromToΔReason on record
130 Jun 202029 Dec 2020+6moSix months extension in view of force...
229 Dec 202029 Dec 2021+12mo
329 Dec 202128 Sep 2022+9mo
Net slip vs first declared date+27moto 28 Sep 2022

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Kindle Infraheights Private Limited
Type
Company
Registered office
C-60 PREET VIHAR DELHI
Projects on the register
1
Complaints · promoter-wide
303303 (Under Registration - 5 )
Complaints · this project
282filed against Sikka Kaamna Greens

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

06

Frequently asked

Is Sikka Kaamna Greens RERA registered?

Yes. Sikka Kaamna Greens is registered with UP-RERA under registration number UPRERAPRJ5596, registered on 03 Aug 2017.

Is Sikka Kaamna Greens delayed?

Yes. It was declared for completion by 30 Jun 2020, but the date on record is now 28 Sep 2022, a slip of about 27 months across 3 registered extensions.

Who is the developer of Sikka Kaamna Greens?

Kindle Infraheights Private Limited, which has 1 project(s) registered with UP-RERA and 303 complaint(s) on record across its projects.

How many complaints are filed against Sikka Kaamna Greens?

282 complaint(s) are recorded against Sikka Kaamna Greens specifically on the UP-RERA portal.

Where can I verify Sikka Kaamna Greens's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ5596. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Sikka Kaamna Greens. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation