Ongoing 18-month delay UPRERAPRJ8614

Panchsheel Pratistha Phase - 3 (Tower - T8)

by Valuent Infradevelopers Private Limited · Gautam Buddha Nagar

Completion on record
24 Nov 2021
Declared 25 May 2020 · slipped 18 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ8614
Gautam Buddha Nagar
Registered
11 Aug 2017
Type: Ongoing
Proposed period
30 mo
Declared completion
25 May 2020
original commitment
Latest on record
24 Nov 2021
after 2 extensions
Documents on portal
17
filed with UP-RERA
01

Registration details

Project name
Panchsheel Pratistha Phase - 3 (Tower - T8)
RERA registration no.
UPRERAPRJ8614
Registration type
Ongoing
Registration date
11 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+18months later than promised

Declared completion moved from 25 May 2020 to 24 Nov 2021 over 2 registered extensions.

#FromToΔReason on record
125 May 202024 Nov 2020+6moSix months extension in view of force...
224 Nov 202024 Nov 2021+12mo
Net slip vs first declared date+18moto 24 Nov 2021

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Valuent Infradevelopers Private Limited
Type
Company
Registered office
H-169 sector 63 Noida, Gautam Buddha Nagar, U.P.
Projects on the register
3
Complaints · promoter-wide
1313 (Under Registration - 0 )
Complaints · this project
0filed against Panchsheel Pratistha...

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Panchsheel Pratistha Phase - 3 (Tower - T8) RERA registered?

Yes. Panchsheel Pratistha Phase - 3 (Tower - T8) is registered with UP-RERA under registration number UPRERAPRJ8614, registered on 11 Aug 2017.

Is Panchsheel Pratistha Phase - 3 (Tower - T8) delayed?

Yes. It was declared for completion by 25 May 2020, but the date on record is now 24 Nov 2021, a slip of about 18 months across 2 registered extensions.

Who is the developer of Panchsheel Pratistha Phase - 3 (Tower - T8)?

Valuent Infradevelopers Private Limited, which has 3 project(s) registered with UP-RERA and 13 complaint(s) on record across its projects.

How many complaints are filed against Panchsheel Pratistha Phase - 3 (Tower - T8)?

0 complaint(s) are recorded against Panchsheel Pratistha Phase - 3 (Tower - T8) specifically on the UP-RERA portal.

Where can I verify Panchsheel Pratistha Phase - 3 (Tower - T8)'s RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ8614. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Panchsheel Pratistha Phase - 3 (Tower - T8). Straight answers, before you sign anything.