Ongoing 51-month delay UPRERAPRJ4746

Nx One

by S.p.sai.it.pvt. Ltd · Gautam Buddha Nagar

Completion on record
25 Nov 2027
Declared 29 Aug 2023 · slipped 51 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ4746
Gautam Buddha Nagar
Registered
01 Aug 2017
Type: Ongoing
Proposed period
127 mo
Declared completion
29 Aug 2023
original commitment
Latest on record
25 Nov 2027
after 3 extensions
Documents on portal
97
filed with UP-RERA
01

Registration details

Project name
Nx One
RERA registration no.
UPRERAPRJ4746
Registration type
Ongoing
Registration date
01 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+51months later than promised

Declared completion moved from 29 Aug 2023 to 25 Nov 2027 over 3 registered extensions.

#FromToΔReason on record
129 Aug 202328 Feb 2024+6moSix months extension in view of force...
228 Feb 202426 Nov 2025+21mo
326 Nov 202525 Nov 2027+24mo
Net slip vs first declared date+51moto 25 Nov 2027

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
S.p.sai.it.pvt. Ltd
Type
Company
Registered office
A-115, Office No-301, Old No.-51, 3rd Floor, Gali No.-1, Vakil Chamber, SHA, Karpur, East Delhi, New Delhi-110092
Projects on the register
4
Complaints · promoter-wide
169169 (Under Registration - 2 )
Complaints · this project
114filed against Nx One

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Nx One RERA registered?

Yes. Nx One is registered with UP-RERA under registration number UPRERAPRJ4746, registered on 01 Aug 2017.

Is Nx One delayed?

Yes. It was declared for completion by 29 Aug 2023, but the date on record is now 25 Nov 2027, a slip of about 51 months across 3 registered extensions.

Who is the developer of Nx One?

S.P.Sai.It.Pvt. Ltd, which has 4 project(s) registered with UP-RERA and 169 complaint(s) on record across its projects.

How many complaints are filed against Nx One?

114 complaint(s) are recorded against Nx One specifically on the UP-RERA portal.

Where can I verify Nx One's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ4746. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Nx One. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation