Ongoing 11-month delay UPRERAPRJ7184

Noida World One - Phase 1

by Cbs International Projects Private Limited · Gautam Buddha Nagar

Completion on record
30 Nov 2020
Declared 01 Dec 2019 · slipped 11 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ7184
Gautam Buddha Nagar
Registered
31 Jul 2017
Type: Ongoing
Proposed period
43 mo
Declared completion
01 Dec 2019
original commitment
Latest on record
30 Nov 2020
after 2 extensions
Documents on portal
23
filed with UP-RERA
01

Registration details

Project name
Noida World One - Phase 1
RERA registration no.
UPRERAPRJ7184
Registration type
Ongoing
Registration date
31 Jul 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+11months later than promised

Declared completion moved from 01 Dec 2019 to 30 Nov 2020 over 2 registered extensions.

#FromToΔReason on record
101 Dec 201901 Jun 2020+6mo
201 Jun 202030 Nov 2020+5moSix months extension in view of force...
Net slip vs first declared date+11moto 30 Nov 2020

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Cbs International Projects Private Limited
Type
Company
Registered office
PLOT NO. 01, SECTOR - 90, NOIDA, GAUTAM BUDH NAGAR, U. P. - 201305
Projects on the register
5
Complaints · promoter-wide
2222 (Under Registration - 0 )
Complaints · this project
11filed against Noida World One - Phase 1

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Noida World One - Phase 1 RERA registered?

Yes. Noida World One - Phase 1 is registered with UP-RERA under registration number UPRERAPRJ7184, registered on 31 Jul 2017.

Is Noida World One - Phase 1 delayed?

Yes. It was declared for completion by 01 Dec 2019, but the date on record is now 30 Nov 2020, a slip of about 11 months across 2 registered extensions.

Who is the developer of Noida World One - Phase 1?

Cbs International Projects Private Limited, which has 5 project(s) registered with UP-RERA and 22 complaint(s) on record across its projects.

How many complaints are filed against Noida World One - Phase 1?

11 complaint(s) are recorded against Noida World One - Phase 1 specifically on the UP-RERA portal.

Where can I verify Noida World One - Phase 1's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ7184. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Noida World One - Phase 1. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation