Ongoing 6-month delay UPRERAPRJ6418

Mangalya Ophira

by Mangalya Buildtech Private Limited · Gautam Buddha Nagar

Completion on record
29 Dec 2019
Declared 30 Jun 2019 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ6418
Gautam Buddha Nagar
Registered
31 Jul 2017
Type: Ongoing
Proposed period
65 mo
Declared completion
30 Jun 2019
original commitment
Latest on record
29 Dec 2019
after 1 extension
Documents on portal
18
filed with UP-RERA
01

Registration details

Project name
Mangalya Ophira
RERA registration no.
UPRERAPRJ6418
Registration type
Ongoing
Registration date
31 Jul 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 30 Jun 2019 to 29 Dec 2019 over 1 registered extension.

#FromToΔReason on record
130 Jun 201929 Dec 2019+6mo
Net slip vs first declared date+6moto 29 Dec 2019

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Mangalya Buildtech Private Limited
Type
Company
Registered office
H-97, SECTOR-63, NOIDA
Projects on the register
1
Complaints · promoter-wide
2222 (Under Registration - 0 )
Complaints · this project
10filed against Mangalya Ophira

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

06

Frequently asked

Is Mangalya Ophira RERA registered?

Yes. Mangalya Ophira is registered with UP-RERA under registration number UPRERAPRJ6418, registered on 31 Jul 2017.

Is Mangalya Ophira delayed?

Yes. It was declared for completion by 30 Jun 2019, but the date on record is now 29 Dec 2019, a slip of about 6 months across 1 registered extension.

Who is the developer of Mangalya Ophira?

Mangalya Buildtech Private Limited, which has 1 project(s) registered with UP-RERA and 22 complaint(s) on record across its projects.

How many complaints are filed against Mangalya Ophira?

10 complaint(s) are recorded against Mangalya Ophira specifically on the UP-RERA portal.

Where can I verify Mangalya Ophira's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ6418. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Mangalya Ophira. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation