Ongoing 18-month delay UPRERAPRJ6205

India Trade Centre

by Omaxe India Trade Centre Private Limited · Gautam Buddha Nagar

Completion on record
28 Jun 2022
Declared 31 Dec 2020 · slipped 18 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ6205
Gautam Buddha Nagar
Registered
31 Jul 2017
Type: Ongoing
Proposed period
83 mo
Declared completion
31 Dec 2020
original commitment
Latest on record
28 Jun 2022
after 2 extensions
Documents on portal
18
filed with UP-RERA
01

Registration details

Project name
India Trade Centre
RERA registration no.
UPRERAPRJ6205
Registration type
Ongoing
Registration date
31 Jul 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+18months later than promised

Declared completion moved from 31 Dec 2020 to 28 Jun 2022 over 2 registered extensions.

#FromToΔReason on record
131 Dec 202029 Jun 2021+6moSix months extension in view of force...
229 Jun 202128 Jun 2022+12mo
Net slip vs first declared date+18moto 28 Jun 2022

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Omaxe India Trade Centre Private Limited
Type
Company
Registered office
10, Local Shopping Centre Kalkaji, New Delhi Dl-110019 IN
Projects on the register
1
Complaints · promoter-wide
7171 (Under Registration - 0 )
Complaints · this project
59filed against India Trade Centre

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

06

Frequently asked

Is India Trade Centre RERA registered?

Yes. India Trade Centre is registered with UP-RERA under registration number UPRERAPRJ6205, registered on 31 Jul 2017.

Is India Trade Centre delayed?

Yes. It was declared for completion by 31 Dec 2020, but the date on record is now 28 Jun 2022, a slip of about 18 months across 2 registered extensions.

Who is the developer of India Trade Centre?

Omaxe India Trade Centre Private Limited, which has 1 project(s) registered with UP-RERA and 71 complaint(s) on record across its projects.

How many complaints are filed against India Trade Centre?

59 complaint(s) are recorded against India Trade Centre specifically on the UP-RERA portal.

Where can I verify India Trade Centre's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ6205. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind India Trade Centre. Straight answers, before you sign anything.

Speak with an advisor