Ongoing 15-month delay UPRERAPRJ1005

Group Housing Cgewho Phase I

by Central Government Employees Welfare Housing Organ · Gautam Buddha Nagar

Completion on record
27 May 2022
Declared 28 Feb 2021 · slipped 15 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ1005
Gautam Buddha Nagar
Registered
01 Aug 2017
Type: Ongoing
Proposed period
60 mo
Declared completion
28 Feb 2021
original commitment
Latest on record
27 May 2022
after 2 extensions
Documents on portal
1
filed with UP-RERA
01

Registration details

Project name
Group Housing Cgewho Phase I
RERA registration no.
UPRERAPRJ1005
Registration type
Ongoing
Registration date
01 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
PLOT NO.7
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+15months later than promised

Declared completion moved from 28 Feb 2021 to 27 May 2022 over 2 registered extensions.

#FromToΔReason on record
128 Feb 202127 Aug 2021+6moSix months extension in view of force...
227 Aug 202127 May 2022+9mo
Net slip vs first declared date+15moto 27 May 2022

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Central Government Employees Welfare Housing Organ
Type
Societies
Registered office
6TH FLOOR , JANPATH BHAWAN, A WING ,JANPATH NEW DELHI 01
Projects on the register
2
Complaints · promoter-wide
66 (Under Registration - 0 )
Complaints · this project
5filed against Group Housing Cgewho Phase I

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

04

Documents on record

1 document filed on the UP-RERA portal for UPRERAPRJ1005. Each opens on the official portal record.

Filed with the registration
07

Frequently asked

Is Group Housing Cgewho Phase I RERA registered?

Yes. Group Housing Cgewho Phase I is registered with UP-RERA under registration number UPRERAPRJ1005, registered on 01 Aug 2017.

Is Group Housing Cgewho Phase I delayed?

Yes. It was declared for completion by 28 Feb 2021, but the date on record is now 27 May 2022, a slip of about 15 months across 2 registered extensions.

Who is the developer of Group Housing Cgewho Phase I?

Central Government Employees Welfare Housing Organ, which has 2 project(s) registered with UP-RERA and 6 complaint(s) on record across its projects.

How many complaints are filed against Group Housing Cgewho Phase I?

5 complaint(s) are recorded against Group Housing Cgewho Phase I specifically on the UP-RERA portal.

Where can I verify Group Housing Cgewho Phase I's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ1005. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Group Housing Cgewho Phase I. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation