New 6-month delay UPRERAPRJ14252

Godrej Nest Phase-2

by Brick Rise Developers Pvt. Ltd. · Gautam Buddha Nagar

Completion on record
29 Mar 2025
Declared 30 Sep 2024 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ14252
Gautam Buddha Nagar
Registered
03 Nov 2017
Type: New
Proposed period
72 mo
from 01 Oct 2018
Declared completion
30 Sep 2024
original commitment
Latest on record
29 Mar 2025
after 1 extension
Documents on portal
42
filed with UP-RERA
01

Registration details

Project name
Godrej Nest Phase-2
RERA registration no.
UPRERAPRJ14252
Registration type
New
Registration date
03 Nov 2017
Proposed start
01 Oct 2018
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 30 Sep 2024 to 29 Mar 2025 over 1 registered extension.

#FromToΔReason on record
130 Sep 202429 Mar 2025+6moSix months extension in view of force...
Net slip vs first declared date+6moto 29 Mar 2025

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Brick Rise Developers Pvt. Ltd.
Type
Company
Registered office
7th Floor, Tower B, Plot No.8, Sector 127, Noida-201301
Projects on the register
3
Complaints · promoter-wide
2121 (Under Registration - 1 )
Complaints · this project
5filed against Godrej Nest Phase-2

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Godrej Nest Phase-2 RERA registered?

Yes. Godrej Nest Phase-2 is registered with UP-RERA under registration number UPRERAPRJ14252, registered on 03 Nov 2017.

Is Godrej Nest Phase-2 delayed?

Yes. It was declared for completion by 30 Sep 2024, but the date on record is now 29 Mar 2025, a slip of about 6 months across 1 registered extension.

Who is the developer of Godrej Nest Phase-2?

Brick Rise Developers Pvt. Ltd., which has 3 project(s) registered with UP-RERA and 21 complaint(s) on record across its projects.

How many complaints are filed against Godrej Nest Phase-2?

5 complaint(s) are recorded against Godrej Nest Phase-2 specifically on the UP-RERA portal.

Where can I verify Godrej Nest Phase-2's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ14252. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Godrej Nest Phase-2. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation