New 70-month delay UPRERAPRJ15254

Galactic City-Universal Tower

by Homes Connect Developers Private Limited · N/A

Completion on record
31 Dec 2027
Declared 28 Feb 2022 · slipped 70 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ15254
Gautam Buddha Nagar
Registered
21 Feb 2018
Type: New
Proposed period
48 mo
from 01 Mar 2018
Declared completion
28 Feb 2022
original commitment
Latest on record
31 Dec 2027
after 2 extensions
Documents on portal
9
filed with UP-RERA
01

Registration details

Project name
Galactic City-Universal Tower
RERA registration no.
UPRERAPRJ15254
Registration type
New
Registration date
21 Feb 2018
Proposed start
01 Mar 2018
District / tehsil
Gautam Buddha NagarN/A
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+70months later than promised

Declared completion moved from 28 Feb 2022 to 31 Dec 2027 over 2 registered extensions.

#FromToΔReason on record
128 Feb 202227 Aug 2022+6moSix months extension in view of force...
227 Aug 202231 Dec 2027+64mo
Net slip vs first declared date+70moto 31 Dec 2027

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Homes Connect Developers Private Limited
Type
Company
Registered office
A-19, Sector-64, Noida, Uttar Pradesh-201301
Projects on the register
1
Complaints · promoter-wide
1111 (Under Registration - 1 )
Complaints · this project
10filed against Galactic City-Universal Tower

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

06

Frequently asked

Is Galactic City-Universal Tower RERA registered?

Yes. Galactic City-Universal Tower is registered with UP-RERA under registration number UPRERAPRJ15254, registered on 21 Feb 2018.

Is Galactic City-Universal Tower delayed?

Yes. It was declared for completion by 28 Feb 2022, but the date on record is now 31 Dec 2027, a slip of about 70 months across 2 registered extensions.

Who is the developer of Galactic City-Universal Tower?

Homes Connect Developers Private Limited, which has 1 project(s) registered with UP-RERA and 11 complaint(s) on record across its projects.

How many complaints are filed against Galactic City-Universal Tower?

10 complaint(s) are recorded against Galactic City-Universal Tower specifically on the UP-RERA portal.

Where can I verify Galactic City-Universal Tower's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ15254. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Galactic City-Universal Tower. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation