Ongoing 91-month delay UPRERAPRJ7361

Future Estate (Phase-Fe-1)

by Futureworld Greenhomes Pvt. Ltd. · Gautam Buddha Nagar

Completion on record
31 Jul 2026
Declared 31 Dec 2018 · slipped 91 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ7361
Gautam Buddha Nagar
Registered
14 Aug 2017
Type: Ongoing
Proposed period
42 mo
Declared completion
31 Dec 2018
original commitment
Latest on record
31 Jul 2026
after 6 extensions
Documents on portal
23
filed with UP-RERA
01

Registration details

Project name
Future Estate (Phase-Fe-1)
RERA registration no.
UPRERAPRJ7361
Registration type
Ongoing
Registration date
14 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+91months later than promised

Declared completion moved from 31 Dec 2018 to 31 Jul 2026 over 6 registered extensions.

#FromToΔReason on record
131 Dec 201831 Dec 2019+12mo
231 Dec 201930 May 2020+5mo
330 May 202029 Nov 2020+6moSix months extension in view of force...
429 Nov 202031 Mar 2021+4mo
531 Mar 202131 Jul 2025+52mo
631 Jul 202531 Jul 2026+12mo
Net slip vs first declared date+91moto 31 Jul 2026

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Futureworld Greenhomes Pvt. Ltd.
Type
Company
Registered office
M-6, S/F, Kalkaji South Delhi, New DELHI 110092
Projects on the register
7
Complaints · promoter-wide
253253 (Under Registration - 7 )
Complaints · this project
68filed against Future Estate (Phase-Fe-1)

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Future Estate (Phase-Fe-1) RERA registered?

Yes. Future Estate (Phase-Fe-1) is registered with UP-RERA under registration number UPRERAPRJ7361, registered on 14 Aug 2017.

Is Future Estate (Phase-Fe-1) delayed?

Yes. It was declared for completion by 31 Dec 2018, but the date on record is now 31 Jul 2026, a slip of about 91 months across 6 registered extensions.

Who is the developer of Future Estate (Phase-Fe-1)?

Futureworld Greenhomes Pvt. Ltd., which has 7 project(s) registered with UP-RERA and 253 complaint(s) on record across its projects.

How many complaints are filed against Future Estate (Phase-Fe-1)?

68 complaint(s) are recorded against Future Estate (Phase-Fe-1) specifically on the UP-RERA portal.

Where can I verify Future Estate (Phase-Fe-1)'s RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ7361. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Future Estate (Phase-Fe-1). Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation