Ongoing 52-month delay UPRERAPRJ7195

F Premiere (Phase 3)

by Home And Soul Infratech Private Limited · Dadri

Completion on record
09 Jul 2026
Declared 30 Mar 2022 · slipped 52 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ7195
Gautam Buddha Nagar
Registered
01 Aug 2017
Type: Ongoing
Proposed period
89 mo
Declared completion
30 Mar 2022
original commitment
Latest on record
09 Jul 2026
after 4 extensions
Documents on portal
14
filed with UP-RERA
01

Registration details

Project name
F Premiere (Phase 3)
RERA registration no.
UPRERAPRJ7195
Registration type
Ongoing
Registration date
01 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarDadri
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+52months later than promised

Declared completion moved from 30 Mar 2022 to 09 Jul 2026 over 4 registered extensions.

#FromToΔReason on record
130 Mar 202229 Sep 2022+6moSix months extension in view of force...
229 Sep 202228 Jun 2024+21mo
328 Jun 202410 Jul 2025+13mo
410 Jul 202509 Jul 2026+12mo
Net slip vs first declared date+52moto 09 Jul 2026

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Home And Soul Infratech Private Limited
Type
Company
Registered office
ASPIRE 2-701, SUPERTECH EMERALD COURT, SECTOR 93B, NOIDA, (U.P.)
Projects on the register
4
Complaints · promoter-wide
5353 (Under Registration - 2 )
Complaints · this project
9filed against F Premiere (Phase 3)

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is F Premiere (Phase 3) RERA registered?

Yes. F Premiere (Phase 3) is registered with UP-RERA under registration number UPRERAPRJ7195, registered on 01 Aug 2017.

Is F Premiere (Phase 3) delayed?

Yes. It was declared for completion by 30 Mar 2022, but the date on record is now 09 Jul 2026, a slip of about 52 months across 4 registered extensions.

Who is the developer of F Premiere (Phase 3)?

Home And Soul Infratech Private Limited, which has 4 project(s) registered with UP-RERA and 53 complaint(s) on record across its projects.

How many complaints are filed against F Premiere (Phase 3)?

9 complaint(s) are recorded against F Premiere (Phase 3) specifically on the UP-RERA portal.

Where can I verify F Premiere (Phase 3)'s RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ7195. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind F Premiere (Phase 3). Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation