Registration details
- Project name
- Devika Gold Homz
- RERA registration no.
- UPRERAPRJ5398
- Registration type
- Ongoing
- Registration date
- 01 Aug 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarDadri
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 31 Dec 2019 to 29 Dec 2020 over 2 registered extensions.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 31 Dec 2019 | 30 Jun 2020 | +6mo | — |
| 2 | 30 Jun 2020 | 29 Dec 2020 | +6mo | Six months extension in view of force... |
| Net slip vs first declared date | +12mo | to 29 Dec 2020 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Devika Gold Homz Pvt. Ltd.
- Type
- Company
- Registered office
- STILT FLOOR, DEVIKA TOWER, 6 NEHRU PLACE, NEW DELHI-110019
- Projects on the register
- 1
- Complaints · promoter-wide
- 9393 (Under Registration - 1 )
- Complaints · this project
- 74filed against Devika Gold Homz
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
28 documents filed on the UP-RERA portal for UPRERAPRJ5398. Each opens on the official portal record.
Other projects nearby
Frequently asked
Is Devika Gold Homz RERA registered?
Yes. Devika Gold Homz is registered with UP-RERA under registration number UPRERAPRJ5398, registered on 01 Aug 2017.
Is Devika Gold Homz delayed?
Yes. It was declared for completion by 31 Dec 2019, but the date on record is now 29 Dec 2020, a slip of about 12 months across 2 registered extensions.
Who is the developer of Devika Gold Homz?
Devika Gold Homz Pvt. Ltd., which has 1 project(s) registered with UP-RERA and 93 complaint(s) on record across its projects.
How many complaints are filed against Devika Gold Homz?
74 complaint(s) are recorded against Devika Gold Homz specifically on the UP-RERA portal.
Where can I verify Devika Gold Homz's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ5398. This page mirrors that public record for convenience.