Registration details
- Project name
- Delta City Centre
- RERA registration no.
- UPRERAPRJ10308
- Registration type
- Ongoing
- Registration date
- 13 Aug 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 09 Oct 2019 to 07 Apr 2021 over 2 registered extensions.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 09 Oct 2019 | 08 Oct 2020 | +12mo | — |
| 2 | 08 Oct 2020 | 07 Apr 2021 | +6mo | Six months extension in view of force... |
| Net slip vs first declared date | +18mo | to 07 Apr 2021 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Startle Infrastructure Private Limited
- Type
- Company
- Registered office
- GF-3, JB-11C, GUPT COLONY, KHIRKI ENTENSION, MALVIYA NAGAR, DELHI
- Projects on the register
- 1
- Complaints · promoter-wide
- 00 (Under Registration - 0 )
- Complaints · this project
- 0filed against Delta City Centre
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
26 documents filed on the UP-RERA portal for UPRERAPRJ10308. Each opens on the official portal record.
Other projects nearby
Frequently asked
Is Delta City Centre RERA registered?
Yes. Delta City Centre is registered with UP-RERA under registration number UPRERAPRJ10308, registered on 13 Aug 2017.
Is Delta City Centre delayed?
Yes. It was declared for completion by 09 Oct 2019, but the date on record is now 07 Apr 2021, a slip of about 18 months across 2 registered extensions.
Who is the developer of Delta City Centre?
Startle Infrastructure Private Limited, which has 1 project(s) registered with UP-RERA and 0 complaint(s) on record across its projects.
How many complaints are filed against Delta City Centre?
0 complaint(s) are recorded against Delta City Centre specifically on the UP-RERA portal.
Where can I verify Delta City Centre's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ10308. This page mirrors that public record for convenience.