Registration details
- Project name
- Capital City
- RERA registration no.
- UPRERAPRJ7063
- Registration type
- Ongoing
- Registration date
- 31 Jul 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 30 Jun 2020 to 29 Dec 2020 over 1 registered extension.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 30 Jun 2020 | 29 Dec 2020 | +6mo | Six months extension in view of force... |
| Net slip vs first declared date | +6mo | to 29 Dec 2020 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Bptp Limited
- Type
- Company
- Registered office
- OT-14, 3RD FLOOR NEXT DOOR PARKLANDS SECTOR 76 FARIDABAD HARYANA-121004
- Projects on the register
- 1
- Complaints · promoter-wide
- 4040 (Under Registration - 0 )
- Complaints · this project
- 29filed against Capital City
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
31 documents filed on the UP-RERA portal for UPRERAPRJ7063. Each opens on the official portal record.
Other projects nearby
Frequently asked
Is Capital City RERA registered?
Yes. Capital City is registered with UP-RERA under registration number UPRERAPRJ7063, registered on 31 Jul 2017.
Is Capital City delayed?
Yes. It was declared for completion by 30 Jun 2020, but the date on record is now 29 Dec 2020, a slip of about 6 months across 1 registered extension.
Who is the developer of Capital City?
Bptp Limited, which has 1 project(s) registered with UP-RERA and 40 complaint(s) on record across its projects.
How many complaints are filed against Capital City?
29 complaint(s) are recorded against Capital City specifically on the UP-RERA portal.
Where can I verify Capital City's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ7063. This page mirrors that public record for convenience.