Registration details
- Project name
- Bhs-17 Lohiya Enclave Omicron-1a
- RERA registration no.
- UPRERAPRJ9632
- Registration type
- Ongoing
- Registration date
- 14 Aug 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 23 Jun 2019 to 20 Feb 2020 over 2 registered extensions.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 23 Jun 2019 | 31 Dec 2019 | +6mo | — |
| 2 | 31 Dec 2019 | 20 Feb 2020 | +2mo | — |
| Net slip vs first declared date | +8mo | to 20 Feb 2020 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Greater Noida Industrial Development Authority
- Type
- Competent authority
- Registered office
- PLOT NO-01, KNOWLEDGE PARK-04, GREATER NOIDA, G.B. NAGAR UP
- Projects on the register
- 10
- Complaints · promoter-wide
- 270270 (Under Registration - 0 )
- Complaints · this project
- 45filed against Bhs-17 Lohiya...
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
39 documents filed on the UP-RERA portal for UPRERAPRJ9632. Each opens on the official portal record.
More from Greater Noida...
Other projects nearby
Frequently asked
Is Bhs-17 Lohiya Enclave Omicron-1A RERA registered?
Yes. Bhs-17 Lohiya Enclave Omicron-1A is registered with UP-RERA under registration number UPRERAPRJ9632, registered on 14 Aug 2017.
Is Bhs-17 Lohiya Enclave Omicron-1A delayed?
Yes. It was declared for completion by 23 Jun 2019, but the date on record is now 20 Feb 2020, a slip of about 8 months across 2 registered extensions.
Who is the developer of Bhs-17 Lohiya Enclave Omicron-1A?
Greater Noida Industrial Development Authority, which has 10 project(s) registered with UP-RERA and 270 complaint(s) on record across its projects.
How many complaints are filed against Bhs-17 Lohiya Enclave Omicron-1A?
45 complaint(s) are recorded against Bhs-17 Lohiya Enclave Omicron-1A specifically on the UP-RERA portal.
Where can I verify Bhs-17 Lohiya Enclave Omicron-1A's RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ9632. This page mirrors that public record for convenience.