Registration details
- Project name
- Belvedere (Phase - 2: Tower E F & G)
- RERA registration no.
- UPRERAPRJ4480
- Registration type
- Ongoing
- Registration date
- 29 Jul 2017
- Proposed start
- —
- District / tehsil
- Gautam Buddha NagarGautam Buddha Nagar
- Project address
- Not stated on the register
- Record source
- up-rera.in
Completion timeline
The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.
Declared completion moved from 31 Dec 2020 to 30 Dec 2022 over 2 registered extensions.
| # | From | To | Δ | Reason on record |
|---|---|---|---|---|
| 1 | 31 Dec 2020 | 30 Jun 2021 | +6mo | Six months extension in view of force... |
| 2 | 30 Jun 2021 | 30 Dec 2022 | +18mo | — |
| Net slip vs first declared date | +24mo | to 30 Dec 2022 | ||
About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.
Promoter track record
The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.
- Promoter
- Sequel Buildcon Pvt. Ltd
- Type
- Company
- Registered office
- Regd. Office-502, Sachdeva Corporate Towers, Plot No.17, Karkardooma Community Centre, Delhi-92
- Projects on the register
- 2
- Complaints · promoter-wide
- 2626 (Under Registration - 0 )
- Complaints · this project
- 8filed against Belvedere (Phase -...
A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.
Documents on record
27 documents filed on the UP-RERA portal for UPRERAPRJ4480. Each opens on the official portal record.
More from Sequel Buildcon Pvt. Ltd
Other projects nearby
Frequently asked
Is Belvedere (Phase - 2: Tower E F & G) RERA registered?
Yes. Belvedere (Phase - 2: Tower E F & G) is registered with UP-RERA under registration number UPRERAPRJ4480, registered on 29 Jul 2017.
Is Belvedere (Phase - 2: Tower E F & G) delayed?
Yes. It was declared for completion by 31 Dec 2020, but the date on record is now 30 Dec 2022, a slip of about 24 months across 2 registered extensions.
Who is the developer of Belvedere (Phase - 2: Tower E F & G)?
Sequel Buildcon Pvt. Ltd, which has 2 project(s) registered with UP-RERA and 26 complaint(s) on record across its projects.
How many complaints are filed against Belvedere (Phase - 2: Tower E F & G)?
8 complaint(s) are recorded against Belvedere (Phase - 2: Tower E F & G) specifically on the UP-RERA portal.
Where can I verify Belvedere (Phase - 2: Tower E F & G)'s RERA details?
On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ4480. This page mirrors that public record for convenience.
Want to go through this file before you commit?
Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Belvedere (Phase - 2: Tower E F & G). Straight answers, before you sign anything.