Ongoing 18-month delay UPRERAPRJ8960

Apex Court

by Apex Infraventures Pvt. Ltd. · Gautam Buddha Nagar

Completion on record
29 Dec 2020
Declared 30 Jun 2019 · slipped 18 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ8960
Gautam Buddha Nagar
Registered
10 Aug 2017
Type: Ongoing
Proposed period
48 mo
Declared completion
30 Jun 2019
original commitment
Latest on record
29 Dec 2020
after 3 extensions
Documents on portal
11
filed with UP-RERA
01

Registration details

Project name
Apex Court
RERA registration no.
UPRERAPRJ8960
Registration type
Ongoing
Registration date
10 Aug 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+18months later than promised

Declared completion moved from 30 Jun 2019 to 29 Dec 2020 over 3 registered extensions.

#FromToΔReason on record
130 Jun 201930 Jun 2020+12mo
230 Jun 201931 Jan 2024+43mo
330 Jun 202029 Dec 2020+-37moSix months extension in view of force...
Net slip vs first declared date+18moto 29 Dec 2020

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Apex Infraventures Pvt. Ltd.
Type
Company
Registered office
F-25, Mansarover Garden New Delhi-110015
Projects on the register
1
Complaints · promoter-wide
66 (Under Registration - 0 )
Complaints · this project
6filed against Apex Court

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

06

Frequently asked

Is Apex Court RERA registered?

Yes. Apex Court is registered with UP-RERA under registration number UPRERAPRJ8960, registered on 10 Aug 2017.

Is Apex Court delayed?

Yes. It was declared for completion by 30 Jun 2019, but the date on record is now 29 Dec 2020, a slip of about 18 months across 3 registered extensions.

Who is the developer of Apex Court?

Apex Infraventures Pvt. Ltd., which has 1 project(s) registered with UP-RERA and 6 complaint(s) on record across its projects.

How many complaints are filed against Apex Court?

6 complaint(s) are recorded against Apex Court specifically on the UP-RERA portal.

Where can I verify Apex Court's RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ8960. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Apex Court. Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation