Ongoing 27-month delay UPRERAPRJ5814

Ambrosia (Phase-1: Tower A B C D & E)

by Ivr Prime Developers (Avadi) Private Limited · Gautam Buddha Nagar

Completion on record
28 Mar 2022
Declared 31 Dec 2019 · slipped 27 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ5814
Gautam Buddha Nagar
Registered
31 Jul 2017
Type: Ongoing
Proposed period
73 mo
Declared completion
31 Dec 2019
original commitment
Latest on record
28 Mar 2022
after 3 extensions
Documents on portal
16
filed with UP-RERA
01

Registration details

Project name
Ambrosia (Phase-1: Tower A B C D & E)
RERA registration no.
UPRERAPRJ5814
Registration type
Ongoing
Registration date
31 Jul 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+27months later than promised

Declared completion moved from 31 Dec 2019 to 28 Mar 2022 over 3 registered extensions.

#FromToΔReason on record
131 Dec 201930 Dec 2020+12mo
230 Dec 202029 Jun 2021+6moSix months extension in view of force...
329 Jun 202128 Mar 2022+9mo
Net slip vs first declared date+27moto 28 Mar 2022

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Ivr Prime Developers (Avadi) Private Limited
Type
Company
Registered office
1114, HEMKUNT CHAMBER, 89, NEHRU PLACE, NEW DELHI-110019
Projects on the register
6
Complaints · promoter-wide
310310 (Under Registration - 0 )
Complaints · this project
46filed against Ambrosia (Phase-1:...

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Ambrosia (Phase-1: Tower A B C D & E) RERA registered?

Yes. Ambrosia (Phase-1: Tower A B C D & E) is registered with UP-RERA under registration number UPRERAPRJ5814, registered on 31 Jul 2017.

Is Ambrosia (Phase-1: Tower A B C D & E) delayed?

Yes. It was declared for completion by 31 Dec 2019, but the date on record is now 28 Mar 2022, a slip of about 27 months across 3 registered extensions.

Who is the developer of Ambrosia (Phase-1: Tower A B C D & E)?

Ivr Prime Developers (Avadi) Private Limited, which has 6 project(s) registered with UP-RERA and 310 complaint(s) on record across its projects.

How many complaints are filed against Ambrosia (Phase-1: Tower A B C D & E)?

46 complaint(s) are recorded against Ambrosia (Phase-1: Tower A B C D & E) specifically on the UP-RERA portal.

Where can I verify Ambrosia (Phase-1: Tower A B C D & E)'s RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ5814. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Ambrosia (Phase-1: Tower A B C D & E). Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation