Ongoing 6-month delay UPRERAPRJ4999

Ajnara City Villa (Phase - 1)

by Ajnara India Limited · Gautam Buddha Nagar

Completion on record
30 Jun 2022
Declared 31 Dec 2021 · slipped 6 months
Speak with an advisor
Overview Timeline Promoter Documents FAQ
RERA number
UPRERAPRJ4999
Gautam Buddha Nagar
Registered
31 Jul 2017
Type: Ongoing
Proposed period
63 mo
Declared completion
31 Dec 2021
original commitment
Latest on record
30 Jun 2022
after 1 extension
Documents on portal
25
filed with UP-RERA
01

Registration details

Project name
Ajnara City Villa (Phase - 1)
RERA registration no.
UPRERAPRJ4999
Registration type
Ongoing
Registration date
31 Jul 2017
Proposed start
District / tehsil
Gautam Buddha NagarGautam Buddha Nagar
Project address
Not stated on the register
Record source
up-rera.in
02

Completion timeline

The completion date declared at registration, and every extension recorded on the register since. Dates are as filed with UP-RERA; a recorded extension is a lawful entry, not a finding of fault.

+6months later than promised

Declared completion moved from 31 Dec 2021 to 30 Jun 2022 over 1 registered extension.

#FromToΔReason on record
131 Dec 202130 Jun 2022+6moSix months extension in view of force...
Net slip vs first declared date+6moto 30 Jun 2022

About 54% of registered projects in this market run past their first promised date. A delay is common here, read it against the promoter's record.

03

Promoter track record

The promoter's wider record on the register, registrations and complaint counts, as filed with UP-RERA.

Promoter
Ajnara India Limited
Type
Company
Registered office
1. B-189, YOJNA VIHAR, DELHI-92 2. B-189, YOJNA VIHAR, DELHI-92 3. B-189, YOJNA VIHAR, DELHI-92 4
Projects on the register
13
Complaints · promoter-wide
342342 (Under Registration - 0 )
Complaints · this project
12filed against Ajnara City Villa (Phase - 1)

A complaint is an allegation filed with UP-RERA, not a finding of wrongdoing, matters may be pending, withdrawn, dismissed, or decided in the promoter's favour. We show the count, as on 07 Jul 2026, so you can ask about it. A completion-date extension is a lawful entry on the register, not an admission of fault.

07

Frequently asked

Is Ajnara City Villa (Phase - 1) RERA registered?

Yes. Ajnara City Villa (Phase - 1) is registered with UP-RERA under registration number UPRERAPRJ4999, registered on 31 Jul 2017.

Is Ajnara City Villa (Phase - 1) delayed?

Yes. It was declared for completion by 31 Dec 2021, but the date on record is now 30 Jun 2022, a slip of about 6 months across 1 registered extension.

Who is the developer of Ajnara City Villa (Phase - 1)?

Ajnara India Limited, which has 13 project(s) registered with UP-RERA and 342 complaint(s) on record across its projects.

How many complaints are filed against Ajnara City Villa (Phase - 1)?

12 complaint(s) are recorded against Ajnara City Villa (Phase - 1) specifically on the UP-RERA portal.

Where can I verify Ajnara City Villa (Phase - 1)'s RERA details?

On the official UP-RERA portal at up-rera.in, under registration number UPRERAPRJ4999. This page mirrors that public record for convenience.

Want to go through this file before you commit?

Speak with an advisor who has actually read this file, the delay history, the complaints, the paperwork behind Ajnara City Villa (Phase - 1). Straight answers, before you sign anything.

Speak with an advisor

Private line · no obligation